单选题

Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage,retrieval, and ultimate disposition ofproject information.

AIntegration

BTime

CPlanning

DCommunication

正确答案

来源:www.examk.com

答案解析

该题的关键词较多,不过都是并列的关系,包括"ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition、 projectinformation"。其主要语句结构为"Project()Management(主语)is(谓语)the Knowledge Area",含义为"项目什么管理是知识领域",后续的定语从句说明该知识领域的特点。其实根据关键词"Proj ect information"考生可以很容易识别出来应该是项目沟通管理。
相似试题
  • The()provides the project manager with the authority to apply organizational resources to project activities.

    单选题查看答案

  • The most crucial time for project risk assessment is ( ).

    单选题查看答案

  • ()means that every project has a definite beginning and a definite end.

    单选题查看答案

  • In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()

    单选题查看答案

  • The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

    单选题查看答案

  • Project selection methods involve measuring value or attractiveness to the project owner or sponsor and may include other organizational decision criteria ()is not a project selection method.

    单选题查看答案

  • The()defines the phases that connect the beginning of a project to its end.

    单选题查看答案

  • The project()is a key input to quality planning since it documents major project deliverables, the project objectives that serve to define important stakeholder requirements,thresholds, and acceptance criteria.

    单选题查看答案

  • Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().

    单选题查看答案

  • The creation ofa work breakdown structure (WBS) is the process of()the major project deliverables.

    单选题查看答案